Indonesia - Power XXIII Project

The Project covered the construction of the 19 megawatt (MW) Tanggari II hydropower scheme (HPS) in North Sulawesi; the construction of the 210 MW Musi HPS in the southern part of Sumatra; reinforcement of transmission networks in the southern part of Sumatra; installation of waste heat recovery equipment in selected diesel power stations outside Java; implementation of demand side management (DSM) pilot projects; and engineering design of the 340 MW Merangin HPS in the southern part of Sumatra.

Full Evaluation: 

Area of Evaluation: 

Mitigation

Thematic Cluster: 

Renewable energy

Theme of Evaluation: 

Renewable Energy

GEF Funding: 

No

Level of Evaluation: 

Country

Region: 

South Asia

Type of Evaluation: 

Project Completion Report

Country: 

Indonesia

Institution: 

ADB

Year of Evaluation: 

2008